Hungary/Romania: Transboundary River Basin Management of the Körös/Crisuri River Project (#379)

Körös/Crisuri transboundary River Basin is in need of more transboundary cooperation and coordination to ensure sustainable management of the resource. To address this, Romania and Hungary jointly developed a strategy for integrated water resources management, aiming to strengthen cooperation. The key lesson is that access to, and management of data is at the core of decision-making in the case of transboundary water management. 

Description

The five countries bordering the Tisza/Tisa river basin are Romania, Hungary, Slovakia, Ukraine, and Republic of Serbia. The pollution accidents that affected the Tisza/Tisa in early 2000 underlined the need for further strengthening of international cooperation between Romania and Hungary regarding all aspects related to integrated water resource management at river basin level.  Occurrence of frequent floods also means that flood management is a major issue for the basin.

Adopted in 2000, the Water Framework Directive (WFD) requires a number of obligations to be fulfilled with the aim of reaching “good status” for European water resources within fixed deadlines. The International Commission for the Protection of the Danube River (ICPDR) set up a cooperative strategy fully in line with the WFD requirements.

In a project to manage the tributaries of the Danube basin, Tisza sub-basin (Körös/Crisuri Basin) Romania and Hungary applying the requirements of WFD implemented a project in the Körös/Crisuri sub-basin shared between the two countries.

Action taken

Romania and Hungary with the support of French ministry of Ecology and Sustainable Development, FFEM and IOWater developed a pilot integrated water management tool for the Körös/Crisuri transboundary River Basin within the Tisza/Tisa sub-basin. The project, which started in 2005, brought together Hungarian, Romanian and French experts to coordinate and provide technical assistance in the implementation of the WFD.

The project was designed to strengthen cooperation between Hungarian and Romanian organizations responsible for environment and water management. It also aimed at encouraging public participation in the process of developing River Basin Management Plans (RBMPs) in line with WFD requirements and a Watershed Contingency Plan (WCP) to prepare a response to future accidental water pollution.

The project provided support to structure stakeholder involvement in the river management planning process which is expected to enhance active public participation in the Körös /Crisuri basin. In particular the project laid a firm foundation for local and national data base and information management procedures in addition to those promoted by the ICPDR portal and through the Danube River Basin GIS project.

A key tool in the form of a catalogue of metadata and data sources available on internet was set up to enable easy sharing of metadata between international partners involved in the basin management. This has acted as a powerful incitement for data structure harmonization between different administrative bodies in both countries.

The project greatly contributed to the development of a harmonized River Basin Management Plan and Watershed Contingency Plan. The project activities were designed according to the steps necessary for preparing an RBMP which led to the elaboration of one of the very first RBMPs of the Danube basin.

In addition, training on public debate techniques was provided to prepare a public consultation pilot test on the main water issues in several municipalities in both countries water sectors.

Lessons learned

Access to and management of data is at the core of decision making in the case of transboundary water management which is necessary for planning, modeling, map production and public information.

Such information is needed for the development of baseline scenario relating to the evolution of the impact of diffuse pollution from agriculture, to drinking water and wastewater treatment needs, to mining industry discharge, and to anticipating changes in the basin.

Project of this type can create a team work between the practitioners working on water issues in transboundary river basins. In addition, it enhances easy transfer of new methodologies and practices to the regional and national teams responsible for the generalization of the work in their respective countries.

The dissemination of the project results from Tisza/Tisa has acted as an example in the whole of Danube basin not only in Hungary and Romania but other countries.

The integration of economical factors is also realized to be key for sound and efficient progress decision making in water management.